Power plant KAPAR, KEV, 4th block, 300 MW

Country: Malaysia

Customer: Kapar Energy Ventures, in cooperation with Emerson Process Management Asia Pacific

Scope of delivery: Reconstruction of the hydraulic control system 300 MW MHI turbo-set 4th block– independent position control of each control units (6 governing valves, 2 throttle valves, 2 interceptor valves, 2 reheat stop valves and 2 reheat stop trip valve). Complete reconstruction of oil distribution system – installation of a unit for high pressure supply (16 MPa). Installation of new Trip block of Invelt turbine protection system with possibility of hydraulic starting from original protections.

Design, assembly, disassembly, supervision, testing and putting into operation

Realization: 2014 – 2021