Modernization of power outlets in PR 6kV substation
Country: Czech republic
Customer: Teplárny Brno, a.s.
Scope of deliveries:
Modernization of substation PR 6kV switchgears RR23, RR 20 and RR17 for T2, T3 and T4 power outlets.
Wiring design of electric protections, metering system and other components, calculation of setting, parameterization and secondary tests of electric protections, delivery, assembly and wiring of components for modernization of the switchgears in question, especially electric protections, MCBs, including assembly of cabling, project and realization of control system Simatic S7-400 modification, addition of necessary hardware components, modification of PLC application program and visualization software of operator stations dedicated for electrical equipment monitoring and operation including remote operator station situated in the workshop of maintenance electricians.
Term of realization: 2022 – 2023